Dev Server

Warning: This content may not be as expected. This server is for testing and POCs only. visit www.rrc.texas.gov for the actual website.

Seismicity Review

Information for Permitting Disposal Wells in Areas of Seismicity

Application Information

The checklist below outlines the information required for disposal well applications that undergo a seismicity review. Applicants are encouraged to submit any additional information that will assist seismicity review.

Checklist

Checklist Item Description

Area Of Interest (AOI) Map
  • An application for a new disposal well permit or an amendment of an existing disposal well permit for injection pressure, injection rate, or injection interval must include a survey of historical seismic events within 5.64 miles, the Area Of Interest (AOI). For instructions on how to create a survey of historical seismic events see the Historical Seismic Events section of the Attachments for New Injection/Disposal Wells webpage.
  • A seismic event of 2.0 Magnitude (M) or greater from the USGS earthquake catalog or the TexNet earthquake catalog triggers seismicity review and requires additional geologic information across the AOI. A Seismicity Review can be triggered by complex geology (for example, injection into basement or near basement strata with known faulting).

Geologic Information

  • Structure maps on top and bottom of injection interval,
  • Isopach map of the injection interval, and
  • Cross-sections oriented along strike and dip of the formation(s) proposed for injection.

Fault Hazard Analysis

  • If a fault exists within the AOI, a fault hazard analysis may be required. The Stanford Center for Induced and Triggered Seismicity (SCITS) provides a free tool,  Fault Slip Potential, to screen a fault's probablility for slip, using data on the nature of the fault and nearby injection.
  • Applicants are encouraged to submit any additional information that would assist evaluation of seismic hazard.

Permit Conditions

To ensure that disposal permits issued with a seismic event ≥ 2.0M in the AOI do not contribute to seismic activity, permit conditions may be applied for administrative approval, including:

  • Lower permitted injection rate in accordance with seismicity review score,
  • Lower injection pressure if disposal is into a formation with a low fracture gradient,
  • Step-rate test(s),
  • Bottom-hole pressure test(s),
  • Daily recording of injection volumes and pressures, and
  • Permitting conditions recommended by the RRC Seismologist.

Existing Disposal Well Permits

The Commission has the authority to modify, suspend or terminate an injection well permit if the injection well is found to be contributing or likely to be contributing to seismic activity.  In coordination with the RRC Seismologist, Injection-Storage Permits Unit (UIC) will monitor seismicity near injection wells and respond accordingly.

Permian Basin - Additional Information

Applications for disposal well permits in the Permian Basin (Districts 7C, 08 and 8A) should include additional information to assist review of the following seismic hazard factors:

Seismicity and Faulting Factors

  • Number of Mapped Faults in AOI
  • Horizontal Distance to Nearest Mapped Fault
  • Distance from Base of Disposal Zone to Basement or Top of Basement Fault
  • Number of Seismic Events ≥ 2.0M in AOI
  • Horizontal Distance to Seismic Event ≥ 2.0M
  • Maximum Seismic Event Magnitude in AOI
  • Years Since Last Seismic Event in AOI
  • Seismicity & Faulting Data Confidence

Operational Factors

  • Permitted Cumulative Injection Rate within 2.82 mi
  • Distance to Nearest Injection Well in Same Interval(s)

Reservoir Factors

  • Disposal Zone Static Permeability
  • Disposal Zone Cumulative Thickness
  • Disposal Zone Lithology

Seismic Monitoring

Operators are encouraged to perform seismic monitoring. In the Permian Basin (Districts 7C, 08 and 8A), an Operator may be permitted for a higher injection rate if an Operator develops and implements an RRC-approved Seismic Monitoring Plan and an Earthquake Response Plan.

Seismic Monitoring Plan

The Seismic Monitoring Plan must contribute data to an existing public seismic network, for example The University of Texas, Bureau of Economic Geology's TexNet program. TexNet has specified  seismic station requirements. Monitoring should contribute to the body of public knowledge to better resolve earthquake locations, especially depth. At a minimum, the Seismic Monitoring Plan must include:

  • The method of monitoring,
  • The location and type of instrumentation, and
  • An archive of the data in a public seismic database.

Earthquake Response Plan

The Earthquake Response Plan must identify actions that will be taken to inspect for facility damage, mitigate risk by modifying operations, and establish thresholds for suspension of injection activity. At a minimum, the Earthquake Response Plan must include:

  • Monitoring plan will be filed with the Commission before disposal activities begin.
  • Operator will monitor TexNet and USGS catalogs.
  • Response plan triggered when a 3.5M event is detected with a reported hypocenter location within the AOI.
  • Operator will notify the Commission within 24 hours of an earthquake that triggers the response plan.
  • Within 30 days of an earthquake trigger, the operator will file a report with the Commission documenting the event.


Commissioners